Jake can dig a well in 16 days. Paul can dig the same well in 24 days. Jake, Paul and Hari together dig the well in 8 days. Hari alone can dig the well in
96 days
48 days
32 days
24 days
Explanation:
Explanation: Simple one. Let the total work to be done is 48 meters. Now Jake can dig 3 mts, Paul can dig 2 mts a day. Now all of them combined dug in 8 days so per day they dug 48/8 = 6 mts. So Of these 8 mts, Hari capacity is 1 mt.
So he takes 48 /1 = 48 days to complete the digging job.