A, B and C can do a work in 12, 15 and 20 days respectively. They all work for one day. Then B leaves the group. In how many days will A and C complete
the rest of the work?
8 days
7 days
9 days
6 days
A, B and C can do a work in 12, 15 and 20 days respectively. They all work for one day. Then B leaves the group. In how many days will A and C complete
the rest of the work?