36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

12
18
22
24
Explanation:

Let the required number of days be $ x $.

Less men, More days (Indirect Proportion)

$\therefore$ 27 : 36 :: 18 : $ x $    $\Leftrightarrow$    27 x $ x $ = 36 x 18

$\Rightarrow x $ =$ \dfrac{36 \times 18}{27} $

$\Rightarrow x $ = 24.