A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of work finished by C in 2 days.If they get Rs 1500 for the whole work, the daily wages of B and C are?

Rs 225
Rs 25
Rs 250
Rs 20
Explanation:

Let the total work = 30 units.

Then capacity of A = 3 units, B = 2 units. Now they worked for 5 days. So they must have completed 25 units.

Rest of the work 5 units done by C in 2 days. So C capacity = 5/2 = 2.5 units.

Given that toatal wages are Rs.1500 for 30 units. So for 1 unit of work they get Rs.50. Now B and C per day

work = (2 + 2.5) = 4.5 units. So their daily wages = 4.5 $\times$ 50 = Rs.225.